Question on SAP.. I have a line for DEC and EQ has a 90 hour month.
so can SAP down to 75.

but my line value is 84:40 and Obligation says 84:40 becaue of carryover.

can I SAP down to 75 or do I have to SAP down to just 84:40

or can I SAP down to 75 and then just pick up trips to meet obligation of 84"40?

thanks
 
Question on SAP.. I have a line for DEC and EQ has a 90 hour month.
so can SAP down to 75.

but my line value is 84:40 and Obligation says 84:40 becaue of carryover.

can I SAP down to 75 or do I have to SAP down to just 84:40

or can I SAP down to 75 and then just pick up trips to meet obligation of 84"40?

thanks

My SAP does not open until midnight, so I cannot check on this..but I believe one of the first things SAP asks you to do is to choose whether you want to use carryover time or not.

Also, if you change your mind later on, you will probably have to get your supervisor to reset it.

RR
 
Question on SAP.. I have a line for DEC and EQ has a 90 hour month.
so can SAP down to 75.

but my line value is 84:40 and Obligation says 84:40 becaue of carryover.

can I SAP down to 75 or do I have to SAP down to just 84:40

or can I SAP down to 75 and then just pick up trips to meet obligation of 84"40?

thanks
Obligation and SAP floors have no correlation. You can SAP down to the floor of 75 at this point (or whatever your personal floor is, see below).
Your obligation will be reset after SAP closes.
Remember, if you have bank time, you can reduce your SAP floor by the amount of bank. Just type in the new time on page 1 of SAP prior to entering your saps on that page.
Good luck SAP-ping.
Cheers
 
Obligation and SAP floors have no correlation. You can SAP down to the floor of 75 at this point (or whatever your personal floor is, see below).
Your obligation will be reset after SAP closes.
Remember, if you have bank time, you can reduce your SAP floor by the amount of bank. Just type in the new time on page 1 of SAP prior to entering your saps on that page.
Good luck SAP-ping.
Cheers

thanks , that is what I was looking for, the no correlation between the obligation and SAP floor...

also where is the bank time listed? on page 2?